There was no reason to wait any longer. The wall was getting worse every year and I've procrastinated long enough. I've never been afraid to confront a project but this one had a lot of "what ifs".
The wall is not supporting the deck. Its purpose is just to hold back the dirt and gravel under the deck, since whole back yard was "carved" out of a hillside.
In the foreground you can see the natural slope of the rock garden to the right. A few years ago I added the stone wall and flower bed beside the stairs. Actually it held up fairly well considering there was no mortar and the stones were "dry stacked".
What if when I remove the old ties, all the gravel runs out? What if the upright piers supporting the deck are as rotten as the wall?
A recent heat wave made the slugging pretty sweaty on day one and two.
The pictures tell the story. There is just hard labour and not much thinking involved so far.
Steamy hot and humid, the sweat gets in my eyes as I toil.
Using the old stones, I thought I had better add a temporary secondary wall just in case the gravel and dirt up higher decided to slide down. I don't know if it's doing much good though.
Just dig and dig and slug and move. Fortunately by Tuesday a cold front brought much needed relief, but rain slowed me down.
Looking down from the deck you can see how far the wall has moved. It's bowed out about 5 or 6 inches. I wonder how this will impact the paving stones that were added later. I figure I might have to add more pavers once the new wall moves back in line with the deck.
I think if this wall had been in the Carolinas or some place that never freezes it likely wouldn't have moved out as much. What happens is, the water behind the wall (because of poor drainage) freezes and expands each winter and over many years of freeze/thaw cycles, forces the wall to creep outwards. Of course rot and insect damage exacerbates it all and that would even be worse in the Carolinas I guess.
By Wednesday I had a good go at it. I'm encouraged by what I see and am glad I decided to get rid of this rotten mess.
What looked like a big pile of gravel is actually a layer of gravel over clay. It was likely the wet clay that did the damage to the timbers over 35 years or so.
Fortunately the deck's upright piers look to be in good condition. One of my "what if" worries was that there would be rot or insect damage to these important supports. That's a relief. I better make sure I get lots of gravel around them to encourage good drainage and prevent excessive moisture and rot.
At least the clay is holding the bank while I remove the wall.
So far I've been able to do everything myself with no help. I know there will be a lot more slugging and shoveling to get all the wall stones into the back yard and get rid of all the construction debris I've created.
I figured I'll go as far and fast as I can on my own, because soon enough, there will be lots more work to share with Tim jr.